How to write a SWMS in Australia
A SWMS is written by walking the job, not by editing last year's document. This is the sequence that produces a statement a crew can actually follow.
Step 1: confirm a SWMS is required
A SWMS is required for high-risk construction work as defined in the WHS Regulations: work at height above a set threshold, work in or near excavations, work involving asbestos or silica, work near energised electrical installations, and the other listed categories. If the work is not high-risk construction work, a SWMS is not the required document, though your client or contract may still ask for one.
Step 2: describe the work and the site
Name the activity, the location on site, the plant and substances involved, the crew, and the conditions that make this site different: access, ground conditions, adjacent trades, overhead services, weather exposure, public interface. Those conditions are what make the document site-specific rather than generic.
Step 3: break the work into steps
Write the sequence the crew will actually follow, in order, at a level someone could supervise: set up, prepare, carry out, finish, pack down. Most weak SWMS documents fail here by describing the trade rather than the task, so the hazards never attach to a step.
Step 4: identify hazards at each step
For each step, list what could cause harm: falls, falling objects, plant interaction, electrical, hazardous substances, manual tasks, traffic, ground collapse, dust, noise. Include the hazard created by a neighbouring step or trade, because that is where a lot of real incidents come from.
Step 5: rate the risk and choose controls
Rate the risk before controls, choose the control using the hierarchy (eliminate, substitute, engineering, administrative, PPE), then rate the residual risk. Administrative controls and PPE sit at the bottom for a reason: a statement whose only controls are "be careful", a briefing and gloves has not controlled the hazard.
Step 6: assign responsibility and hold points
Every control needs a person responsible and a way it will be checked. Where work must not proceed until verification, state the hold point and who releases it. This is what turns a document into a process on site.
Step 7: consult, sign on and review
Take the draft to the crew who will do the work. They know the site conditions and will find the step you missed. Then sign on: the workers carrying out the work sign the statement before work starts. Set the review triggers: change in work, new hazard, incident, new crew, new plant, or the interval your client requires.
Where SubbieSure fits
SubbieSure includes a Work Method Statement builder for creating and issuing statements per project, with hazards, risk ratings and controls, and sign-off that can be enforced at prestart. See the SWMS app page, or bring your current statement to a demo.
Check the product details
Related reading: free SWMS template guide, SWMS app, toolbox talk app, safety management software, site induction process.
This page is published by SubbieSure and describes our own product, not an independent review or a ranking of vendors. It is general information, not legal or WHS advice. Check requirements for your work, contract and jurisdiction.
Questions about your requirements? Book a demo or email hello@subbiesure.com.